Case Title | Beml Limited |
Court | Karnataka AAAR |
Honorable Judges | Member D.P.Nagendra Kumar & Member Shikha C |
Citation | 2021 (9) GSTPanacea 74 HC Karnataka KAR/AAAR-08/2021 |
Judgement Date | 03-September-2021 |
Council for Petitioner | Nivdange Shweta Shankarrao |
Council for Respondent | Ravi Raghavan Mohammed Ibrahim |
Section | Section 2(30),9(1),97,100,101 |
In Favour of | In Favour of Department (Applicant) |
The Karnataka Bench of Member D.P.Nagendra Kumar & Member Shikha C has held that though there is only one contract, the different activities done as part of the contract, are clearly specified and identifiable. The scope of works undertaken by each cost centres are entirely independent. Hench bench allow the appeal filed by the Assistant Commissioner of Central Tax, Bangalore and set aside the ruling given by the Authority for Advance Ruling with regard to composite supply.
FACTS OF THE CASE
M/s. BEML Limited (hereinafter referred to as “Respondent Company”) have entered into a contract with M/s BMRCL for the manufacture and supply of Standard Gauge Intermediate Cars. The activity of manufacture and supply of Standard Gauge Intermediate Cars involves the supply of both goods and services which is undertaken by Cost Centres A to H.
The value/cost of the supplies specific to each Cost Centres are separately stipulated in the Contract and milestones have been identified for raising of invoices for individual supplies. The Respondent Company is raising separate invoices based on the nature of transactions mentioned in different Cost Centres and accordingly charging GST on separate supplies. The Respondent Company is at present levying tax @ 12% on the supply of Standard Gauge Intermediate Cars and 18% on other supply of services as supplied by the respective Cost Centre
While, BMRCL has paid GST charged relatable to the supplies made by cost centre A and C, they have disputed the payment of GST at the rates charged by the Respondent Company for supplies made vide Cost Centre D, E and G. It is the understanding of BMRCL that the supply for the disputed cost centres are essentially composite supplies taxable at the rate of 5%/ 12% i.e., the rate applicable to principal supply of Rolling stock and that other supplies in the cost centre D to G are incidental and naturally bundled to the principal supply of rolling stock and supplied in conjunction with each other.On account of the disagreement on the nature of supply and applicable tax to be charged, total differential GST of Rs. 19,90,84,844/- stands withheld by BMRCL relatable to cost centres D, E and G.
In view of the above, the Respondent company filed an application for Advance Ruling under Section 97 of the CGST Act, 2017 in respect of the following questions:
I Whether the supplies made by cost centres C, D, E and G to BMRCL are to be considered as independent supplies of goods and services depending upon the scope of the work and applicable GST at the rate of 18% for supply of services and at the rate of 5%/ 12% for supply of goods shall be levied and charged? Consequently, what will be the time of supply for each supplies made by the cost centres?
- Whether the supplies made by cost centres C, D, E and G to BMRCL are to be considered as `composite supply` as defined under Section 2(30) of the CGST Act, 2017 read with Section 9(1) of the CGST Act, 2017, with the supply of intermediate cars undertaken by. Cost Centre C as the principal supply on which GST at 12% shall be levied and charged? Consequently, what will be the classification and time of supply for the entire Contract considering supplies made by Cost Centre C as principal supply?
The Authority for. Advance ruling examined the case of the Respondent arrived at the conclusion that the supplies made by the Respondent Company under Cost Centers C, D, E and G form a composite supply and since the supply of goods i.e intermediate cars is the principal supply, the rate of tax as applicable to the supply of intermediate cars will be applicable to the composite supply in terms of Section 8 of the CGST Act, 2077. The Authority also held that Section 12 of the CGST Act, 2017 is applicable to the issues related to the time of supply
The jurisdictional CGST officer reviewed the impugned order passed by the Authority and being aggrieved by the ruling passed, filed an appeal
The Respondent Company has admitted that each Cost Centre will deliver the indented item on its own; that it was also agreed upon as per the terms of the Contract that agreed amounts would be paid on supply/delivery of intended items/services and against reaching of milestones; that it is clear from the agreement that even the costings in respect of each item of work was worked out by the Respondent Company and the same was accepted by M/s. BMRCL. They submitted that it was a clear and a legally accepted contract between two major businesses who are not new to complex nature of contract/agreement for turnkey projects; that at the time of entering into contract, both the vendor and the customer had mutually agreed to the terms of the contracts fully understanding that billing will be done in accordance with the delivery of goods/services by the respective Cost Centres; that it is evident from the submissions made by M/s. BEML that they have gone by the terms of agreement and billed M/s. BMRCL precisely as per the terms of the agreement. It is only in June,2019, M/s. BMRCL contested that supply as a whole was a Composite supply and lesser rate of GST are applicable.
COURT HELD
Considering the facts as recorded, held that In this case, although there is only one contract, the different activities done by the Cost Centers C, D, E and G as part of the contract, are clearly specified and identifiable. The scope of works undertaken by each Cost Centre C, D, E and G are entirely independent and specific to that cost center and is not associated with any other Cost Centre
bench allow the appeal filed by the Assistant Commissioner of Central Tax, Bangalore and set aside the ruling given by the Authority for Advance Ruling in KAR ADRG 20/2021 dated 6th April 2021 with regard to composite supply
Bench held that the supplies made by Cost Centres C, D, E and G to M/s BMRCL are to be considered as independent supplies of goods and services as indicated in the Table below and rate of GST as applicable to the supply of goods and supply of service will apply
Cost Centre | Schedule of Activity | Treatment of Supply | Applicable GST Rate |
C | Delivery and Receipt of indigenous manufacturing | Supply of Goods | 5% upto 30-09-2019 |
D | Commissioning and acceptance of trains/ cars in depot | Supply of Service | 18% |
E | Taking over of unit/ train for revenue service | Supply of Service | 18% |
G | Supply of unit exchange spares, mandatory spares and consumable spares and special tools, testing and diagnostic equipment. | Supply of Service | 18% / 28% as applicable |
ANALYSIS OF THE JUDGEMENT
The lower Authority has erred in interpreting the creation of cost centres as per the contract as artificial creations to enable cash flow. When interpreting the nature of a contract, the form of the agreement is not important, it is rather the substance which has to be seen. The parties may use any words they like to suit their intention and it is therefore imperative that the agreement may not be taken as it is but its nature/substance has to be seen to arrive at the correct conclusions.
In this case, although a single contract has been made for supply of goods and services, the clear cut demarcation of activities of supply of goods and supply of services to each Cost Centre clearly demonstrates the intention of the contracting parties that each of the cost centres C, D, E and G is an independent supply centre undertaking either a supply of goods or a supply of service.
Hence, bench are unable to subscribe to the views of the lower Authority and the Respondent that the supply of goods and services encompassed as per this contract are naturally bundled. The mere fact that a number of tasks have been entrusted to the Respondent through a single contract would not make it as `composite supply` in terms of Section 2(30) of the CGST Act, 2017. Bench reiterate that the obligations of supplies envisaged in this contract are distinct and separable and hence the separate activities of supply of goods and supply of services have to be viewed independently on its own merits.
Download PDF:
Beml Limited
For Reference Visit:
AAAR Karnataka
Read Another Case Laws:
GST Case Law